More changes, more first articles: AS9102 FAI under the production ramp

Airbus and Boeing are pushing single-aisle rates up while suppliers add capacity, second sources and new processes. Each of those changes can trigger a first article inspection. How to keep AS9102 from becoming the bottleneck.

The single-aisle production ramp is now the backdrop to almost every conversation in the aerospace supply chain. Airbus expects to reach 70 to 75 A320-family aircraft a month by the end of 2027 and to settle at 75 after that [1]. Boeing raised 737 output from 42 to 47 a month in May 2026 and has said it aims for 52 early next year, helped by a fourth production line in Everett [2]. Both companies describe the supply chain, and aerostructures in particular, as a pacing item [1][3].

Rate increases are usually discussed in terms of machines, people and material. Less is said about the paperwork that has to travel with every change a supplier makes to keep up. In aerospace, that paperwork is often a first article inspection.

Why a ramp creates first articles

AS9102, the aerospace standard for first article inspection (FAI), is currently at revision C, published in 2023 [4]. It requires a full or partial FAI not only for a new part, but when certain things change after the first FAI was accepted. The events it lists include design changes that affect fit, form or function, and changes in the manufacturing source, process, inspection method, location or tooling, as well as a long lapse in production. Customers often add their own triggers through their quality clauses, so the list a supplier must follow can be longer than the standard's [5].

Now look at what a supplier does to support a higher rate:

  • adds a second machine or cell, or moves work to a new building or site;
  • brings in a second source for a detail part or a special process;
  • changes NC programs, fixtures or cutting strategies to take time out of a cycle;
  • restarts a part that has not been made for a while.

Each of these can call for a partial or full FAI. A supplier that is growing fast can find that first articles stop being an occasional task and become a steady stream of work that sits directly between production and shipment.

Where FAIs lose time

From preparing and signing off AS9102 reports on nacelle components and other aerospace parts, the delays I see most often have little to do with the measurement itself:

  • Characteristic accountability done by hand. Ballooning a drawing and typing every characteristic into a form 3 is slow and error-prone, and it has to be repeated when the drawing changes.
  • Measurement plans that do not match the drawing. A CMM or tracker program that reports features in a different order, or against a different datum set-up, means hours of reconciliation before the report can be signed.
  • Results with no stated uncertainty. A characteristic measured at 0.048 mm against a 0.050 mm tolerance passes on paper, but nobody can say whether the measurement was good enough to tell. These are the results that get queried by the customer.
  • Rejected reports. Missing references to drawings and specifications, incomplete special process evidence and unclear partial-FAI scope are common reasons for rejection. GKN Aerospace publishes a list of the mistakes it sees most in supplier FAI reports, and it is worth reading before you submit one [6].

What helps at higher rates

None of the fixes below needs new hardware. They need the measurement process to be designed for repeat use instead of rebuilt for each report.

  • Build the measurement plan from the characteristic list. Number every characteristic once, then make the inspection program report in that numbering. In PolyWorks or a CMM package this is a one-off set-up that turns form 3 into an export rather than a typing exercise.
  • Script the routine parts. Alignment, feature extraction and report formatting are the same every time. Scripting them shortens each FAI and removes a source of operator variation.
  • Know your uncertainty on the tight characteristics. You do not need a full uncertainty budget for every dimension, but you should know it for the ones where the tolerance is small compared with what the instrument can do. Decide in advance what happens when a result falls close to a limit.
  • Scope partial FAIs carefully. A partial FAI should cover the characteristics affected by the change and say why the rest are unaffected. A clear rationale is quicker to approve than a full re-inspection that nobody asked for.
  • Treat the first FAI on a new line as a measurement system check too. If the second cell's results differ from the first cell's, find out whether the parts are different or the measurement is, before production volumes build up.
A quick self-checkIf your next three planned changes each triggered a partial FAI, how many working days would those reports take, and who would prepare them? If the answer is "the same two people who already run inspection", FAI capacity belongs on your ramp plan.

Where to start

Pick the part family with the most planned changes over the next year. Map its characteristics to the inspection program once, script the repeatable steps, and write down the measurement uncertainty for the handful of characteristics that are close to the limit of your equipment. That single part family becomes the template for the rest.

If you would like a second pair of eyes on an FAI process before a ramp, or help preparing AS9102 reports with full characteristic accountability, that is work I do regularly.

References

  1. AIN (19 February 2026). Airbus presses Pratt & Whitney over A320 engine shortages.
  2. Boeing (May 2026). 737 'off and rolling' toward higher production rate, CEO says.
  3. Aviation Week. Airbus pursues rate increases as supplier concerns persist.
  4. SAE International. AS9102C: Aerospace first article inspection requirement. See also the BSI listing.
  5. Lockheed Martin. Q2A quality clause revision log, an example of customer-specific FAI requirements flowed down to suppliers.
  6. GKN Aerospace. AS9102 first article inspection report: common mistakes.
About the author

Hammad Kamran, PhD, is the founder of HK Robotics and Metrology. He was metrology lead on Airbus UK’s AutoRAMP programme, metrology systems lead on Wing of Tomorrow, and an automation and metrology engineer at SAFRAN Nacelles.